COMMISSIONING / ACCEPTANCE TESTING

Accept it before you depend on it.

Replacing more than 30 end-of-life analyzers through tender, factory testing, installation and handover.

PCS Singapore · About 2 min read

My role
Program lead from tender through factory testing, installation and handover.
Constraint
Each replacement had to fit around a continuously operating plant.
Decision
Accept in stages, factory, site, integration and handover, each against written criteria.
Outcome
30+ analyzers replaced; new site measurement standards set.
Acceptance / evidence at every stage
  1. 01Specify

    Acceptance criteria written into the tender.

  2. 02Factory test

    Witnessed against the criteria before shipment.

  3. 03Site test

    Installed, connected and checked in place.

  4. 04Handover

    Documentation, training and spares in place.

If a stage fails

Correct it there; each later stage costs more to fix.

Illustrative acceptance stages, each witnessed against criteria agreed in advance.

PERSONAL CONTRIBUTION

What I contributed

  • Directed a $5M+ program replacing 30+ end-of-life gas chromatographs.
  • Ran a competitive multi-vendor tender and technical evaluation.
  • Led factory acceptance testing and site implementation.

The situation

Process gas chromatographs measure stream composition continuously, and the plant relies on their readings. More than 30 of them had reached the end of their supported life. Replacing them meant choosing a supplier, proving the new systems before they arrived and changing each one over around continuous operation.

What I did

At PCS Singapore, I directed the $5M+ replacement program: a competitive multi-vendor tender, technical evaluation, factory acceptance testing before shipment and site implementation. I also piloted analyzer technologies that went on to set new site measurement standards.

The result

More than 30 analyzers were replaced through staged acceptance, and the pilots established new site measurement standards.

The engineering principle

Each acceptance stage answers a different question. A factory test shows the system was built as specified; site tests show it works in place; integration shows it works with everything around it; handover shows the people inheriting it can run it. Skipping a stage moves its questions to a less convenient time.

INSIDE THE DECISION

What should each acceptance stage prove?

The stages I plan before equipment is ordered.

Test once, on site

What it offers
Fewer test events and less travel.
What it asks of the design
Defects surface late, when fixes cost the most and schedules are tightest.

Accept in stages

What it offers
Find each problem where it is cheapest to fix.
What it asks of the design
Agree criteria, witnesses and evidence for every stage in advance.

Questions for a design review

  1. Write acceptance criteria into the tender, not after the award.
  2. Witness factory tests against those criteria before shipment.
  3. Verify installation and integration with the surrounding systems on site.
  4. Hand over with documentation, training and spares in place.

A system is accepted when the evidence shows it does what it was bought to do, where it will be used, by the people who will run it.

Terms used on this page
Factory acceptance testing
Testing equipment and its software at the supplier, against criteria agreed in advance, before it is shipped and installed.
Gas chromatograph
An analyzer that separates a gas sample into its components and measures how much of each is present.
Analyzer
An instrument that measures what a process stream is made of, rather than just its pressure, temperature or flow.
All terms →

Diagrams are conceptual and do not depict any employer system.